Fall quarter was intended to be used completely for design and proposal writing. The work completed during fall quarter pertained to drawings, analysis, planning and the proposal writing. All designing was completed during fall quarter and construction began in winter.

​

Winter quarter was 100% dedicated to construction of the vehicle. Students completed construction the second week of February and were successful in testing the vehicle before the end of the quarter.

​

Work regarding the budget was also completed during Fall Quarter. Students agreed on set budget of 350$ per team-member and split the spending between the two systems. The entire drive train is intended to cost 300$. The teammates also agreed that 100 hrs of time would be budgeted per quarter. Costing 17500$ at 175$ an hour.

​

Students sucessful remained under-budget until the end of winter quarter.

budget and schedule

Table 5.1

Budget1.png

Table 5.2

schedule.png